Opsource server migration from na1 to na3

Server Name Ip Cpu Total Hdd Siz in GB Data Siz in GB Ram Status
App Gold 10.166.152.18 1 10 2048 Need to Migrate
Load Balancer 10.166.152.16 2 10 3.5 2048 Need to Migrate
Prodapp01 10.166.152.11 4 10+50 42.5 8192 Need to Migrate
prddb-mast01 10.166.152.12 8 10+150 18 12288 Need to Migrate
Prod Slave db 10.166.152.13 4 10+150 104.4 8192 Need to Migrate
prodapp02 10.166.152.19 4 10+50 15.5 8192 Need to Migrate
prodapp03 10.166.152.20 4 10+50 6.2 8192 Need to Migrate
prodcollab01 10.166.152.17 6 10+170 32 16384 Need to Migrate
Steps Steps to migrate machines from Na1 to ⇒ Na3 Network Time
1 Clone existing production machine as an image 00:00:00
2 Install cloned image as a machine 00:00:00
3 Vm tools update 00:00:00
4 Vm tools update clone image 00:00:00
5 Updated vm machine image copy from na1 to na3 00:00:00
6 Change Hard Disk HPF 00:00:00
7 Deploy cloned image in Na3 00:00:00
8 Ip Configuration 00:00:00
9 System Testing as a standalone 00:00:00
10 Application Validation 00:00:00
11 Monitoring Reconfig 00:00:00
12 Final data sync of Db , Data , content . 00:00:00
13 Shut Down of live environment 00:00:00
14 Dns Reconfig 00:00:00